| Date |
Event |
| 1/5/2005 |
Downloaded Solar Generations
Application. This is Nevada's net metering rebate program. |
| 1/7/2005 |
Mailed Solar Generations
application. |
| Jan 2005 |
Designed system is broad terms
(size, mounts) and began contacting vendors. |
| 2/25/2005 |
Placed order for 36 KC120
panels. Got them from Affordable
Solar. |
| 3/1/2005 |
Placed order for 2 Wattsun
AZ-225 trackers, each for 18 KC120. |
| 3/16/2005 |
Met with Joe Pizur of Alternative Energy
Solutions about the system. |
| 3/18/2005 |
Received the KC120 panels. |
| 3/29/2005 |
Talked to Roger Roepke about
engineering my foundations. |
| 4/1/2005 |
Received the AZ-225 trackers. |
| 4/7/2005 |
Met with Elton at Cathexes about
doing a site plan. |
| 4/29/2005 |
Got engineered plans from Roger.
Talked to county plan reviewer about other required elements. |
| 5/2/2005 |
Went to the county at 9 am with
plans and other materials for permit. Some three hours later and 1 trip
to Cathexes to have Elton re-do the site plan, I got the permit.
I guess if you've never done this before, it comes off a bit odd. |
| 5/25/2005 |
Finally got eastern edge of lot
surveyed. Laid out foundations. |
| June 2005 |
Spent some time getting wire,
conduit and other parts to complete the installation. |
| 6/2/2005 |
Dug holes for foundation piers |
| 6/3/2005 |
Cleaned up holes and tied steel
for foundations. |
| 6/6/2005 |
Got inspection for steel and
poured about 12 yards of concrete and finished the tops. |
| 6/10/2005 |
Gave plywood templates to Tony
for welding up the posts. |
| 6/14/2005 |
Dug trench for electrical. Also
moved some boulders and started putting in conduit and wire. |
| 6/16/2005 |
Finished underground conduit and
electrical. |
| 6/17/2005 |
Passed underground electrical
inspection. Ready to close trench. |
| 6/18/2005 |
Buried the trench (thanks,
Sean). |
| 6/20/2005 |
Tony finished the support posts
and
delivered them for powder coating. John went and selected a color. John
is colorblind. This should be interesting. |
| 7/12/2005 |
Tony delivered the posts. He,
Grant and I got them set then plumbed, dry packed and left. Yes, they
were at the powder coaters for over 3 weeks. |
| 7/13/2005 |
Motors set on top of posts,
torque tubes installed, and N-S actuators installed. Ready for the PV's
(almost) |
| 7/14/2005 |
Started PV installation with the
South array. |
| 7/15/2005 |
Finished PV installation on the
North array and did the grounding. |
| 7/18/2005 |
Ran conduit, sensors and wiring
the strings of the South array |
| 7/19/2005 |
Ran conduit, sensors and wiring the strings of the North array |
| 7/25/2005 |
Tested range of motion on
trackers for conduit flex. |
| 7/26/2005 |
Ran flexible conduit for PV
panels on south array. |
| 7/27/2005 |
Ran flexible conduit for PV
panels on north array. Did long wire pull to house. |
| 7/29/2005 |
More conduit installation and
mounted combiner/power supply boxes. |
| 7/30/2005 |
Started testing auto tracking
functions. |
| 8/16/2005 |
Worked with Joe Pizur on the
array wiring. |
| 8/24/2005 |
Completed most of final wiring.
Still waiting on two more fuse holders/fuses. |
| 8/28/2005 |
Full operational test of PV's |
| 9/1/2005 |
County building inspection -- we
passed! |
| 9/2/2005 |
Larry Burton from
Solargenerations came and gave us the final SPP inspection and tagged
the boxes. |
| 9/16/2005 |
Generation meter installed and
we are off and running! |